HomeMy WebLinkAbout05_Geology, Soils, and TopographyDRAFT 5-1 07/10/2024
Chapter 5: Geology, Soils, and Topography
A. INTRODUCTION AND SUMMARY OF FINDINGS
This chapter describes the Project Site’s existing geology, soils, and topography, and analyzes
potential impacts to on-site surface and subsurface geologic resources as a result of the Proposed
Project. Bedrock geology, surface soils, and steep slopes are described based on published data
from the United States Department of Agriculture (USDA) Web Soil Survey, the New York State
Geological Survey, New York State High Resolution Digital Elevation Model data, information
available through Westchester County GIS, and a site-specific Phase I Environmental Site
Assessment (“Phase I ESA”).
The Proposed Action would disturb approximately 20.29 acres of the Project Site (inclusive of the
10.74 acres of the Project Site that were previously disturbed) to demolish the existing buildings
and associated site improvements and construct the 250 new dwelling units, roadways and
associated parking, landscaping, amenities, and stormwater management facilities. As detailed in
the analyses below, the cut/fill activities associated with these improvements, inclusive of the
measures included to avoid and mitigate adverse impacts, would not result in significant adverse
impacts to on-site surface and subsurface geologic resources.
B. EXISTING CONDITIONS
SOILS
Seven soil complexes are situated within or immediately adjacent to the Project Site.
These soil types are described in greater detail in Table 5-1 and depicted on Figure 5-1.
The mapped soils are consistent with areas characterized by hills and/or steep slopes.
Nearly all of these soil complexes are associated with Charlton Fine Sandy Loam or
Charlton Loam (ChB, ChC, ChD, ChE, and ClD). The Charlton soil series typically
represent well-drained soils found on hills and ridges in areas with varying slopes that
range between 3 to 8 percent (ChB); 8 to 15 percent (ChC); 15 to 25 percent (ChD and
ClD); and 25 to 35 percent (ChE). In one area, soils are characterized as part of the
Charlton-Chatfield Complex, where slopes range from 0 to 15 percent and soils are
characterized as very rocky (CrC). These soil complexes and/or their component soil types
are summarized in Table 5-1 and depicted on Figure 5-1.
800 East Main Street Redevelopment
07/10/2024 5-2 DRAFT
Table 5-1
Study Area Soils
Series Name
(Map Symbol)
Soil Horizon
Depth (in) Soil Type Slope (%)
Percentage of
Project Site Drainage Landform
Charlton-
Chatfield, Very
Rocky
(CrC)
Oe: 0 to 2 Moderately decomposed
plant material
0 to 15 0.1% Well-drained Ridges and
hills A: 2 to 4 Fine sandy loam
Bw: 4 to 27 Gravelly fine sandy loam
C: 27 to 65 Gravelly fine sandy loam
Charlton Fine
Sandy Loam
(ChB, ChC, ChD
and ClD)
Ap: 0 to 7 Fine sandy loam ChB: 3 to 8
ChC: 8 to 15
ChD: 15 to 25
ChB: 49.3%
ChC: 30.1%
ChD: 19.6%
Well-drained
Ridges,
ground
moraines,
and hills
Bw: 7 to 22 Gravelly fine sandy loam
C: 22 to 65 Gravelly fine sandy loam
Charlton Loam
(ChE, ClD)
H1: 0 to 8 Loam
ChE: 25 to 35
ClD: 15 to 25
ChE: 0.3%
ClD: 0.01% Well-drained
Till plains,
ridges, and
hills
H2: 8 to 24 Sandy loam
H3: 24 to 60 Sandy loam
Note: See Figure 5-1.
Source: Soil Survey Staff, Natural Resources Conservation Service, U.S. Department of Agriculture. Web Soil Survey.
Available online at http://websoilsurvey.nrcs.usda.gov/. Accessed December 5, 2023.
TOPOGRAPHY
Approximately 10.74 acres of the Project Site have been previously disturbed to
accommodate the current commercial office use. The undeveloped, northern, portion of
the Project Site consists of forested land.
The topography of the currently developed portion of the Project Site ranges from a low
of approximately 456 feet above mean sea level at the entrance to the Project Site, to a
high of approximately 565 feet above sea level in the northern parking area. The currently
developed portion of the Project Site generally slopes from north to south. Among the
undeveloped areas of the Project Site, the highest elevation is 701 feet.
The areas and percentages of the Project Site within each slope category are quantified in
Table 5-2. The Project Site features noticeable changes in topography, with areas of 15
percent or greater slopes comprising 52.4 percent of the Project Site (see Figure 5-2).
Table 5-2
Existing Slopes Within the Project Site (Surveyed Area)
Slope Grade Area (acres) Percent of Site
0% to 10% 9.67 27.2%
10% to 15% 7.22 20.4%
Greater than 15% 18.61 52.4%
Total 35.5 100%
Sources: New York State High Resolution DEM data, Site Design Consultants
GEOLOGY
According to the Surficial Geologic Map of New York Lower Hudson Sheet, retrieved from the
New York State Museum, the Project Site is underlain completely by till (see Figure 5-3). The
Bedrock underlying the Project Site is Biotite-quartz-plagioclase paragneiss. This geology is
derived from the Middle Proterozoic age, and is comprised mostly from metamorphic,
Chapter 5: Geology, Soils, and Topography
DRAFT 5-3 07/10/2024
metasedimentary and paragneiss constituents1 (see Figure 5-4). The Phase I ESA also indicated
that groundwater is likely present within fractured bedrock at the Project Site and likely flows to
the west towards a nearby stream located approximately 500 feet from the Project Site.
C. THE FUTURE WITH THE PROPOSED PROJECT
Approximately 20.29 acres of the Project Site would be disturbed during construction of the
Proposed Project, including the approximately 10.74 acres previously disturbed to construct the
Project Site’s current improvements (see Drawing C-104.2 in Appendix I). The existing and
proposed lot and building coverage of the existing and proposed improvements is shown in Table
5-3. The Proposed Project would increase the building coverage from 1.9 percent to 10.5 percent
and the total impervious coverage from 14.6 percent to 26.2 percent. Mitigation for the increase
in impervious coverage would include the implementation of a comprehensive Stormwater
Pollution Prevention Plan (“SWPPP”), which would outline methods to reduce the amount of
stormwater runoff leaving the Project Site, as well as to improve the quality of the Project Site’s
runoff. Preliminary stormwater management practices have been designed, and are discussed in
Chapter 10, “Stormwater Management.”
Table 5-3
Existing and Proposed Building and Impervious Surface Coverage
Existing Condition Proposed Condition
Total Site Area (acres) 35.5 35.5
Total Permeable area (acres) 30.3 26.2
Total Impervious Area (acres) 5.2 9.3
Percent Impervious 14.6% 26.2%
Total Building Area (acres) 0.7 3.7
Percent Building Coverage 1.9% 10.5%
Note: Totals may not sum due to rounding.
Source: Site Design Consultants, Perkins Eastman
Approximately 8.55 acres of the disturbance required to construct the Proposed Project would
occur on slopes greater than 15 percent and approximately 4.35 acres would occur on slopes
between 10 percent and 15 percent. The remaining 7.39 acres of disturbance would occur on slopes
less than 10 percent. The Proposed Project would require excavation of approximately 90,155
cubic yards of material (i.e., “cut”) and would require approximately 8,319 cubic yards of fill
material, resulting in a net cut of 81,836 cubic yards of earthen material. If all of the net cut
material was removed from the Project Site, approximately 4,546 truck trips would be required,
based on 18 cubic yards per truck. It is anticipated that these trips would be spread out over several
months of the Proposed Project’s construction, such that the number of truck trips per day would
be reduced to a level that would not affect traffic operations. Earthwork would be conducted
pursuant to an excavation and regrading permit issued pursuant to Chapter 248, “Stormwater
Management and Erosion and Sediment Control,” of the Town of Yorktown Code. Pursuant to
that Chapter of the Town’s Code, as well as State requirements, a Soil Erosion and Sediment
Control Plan has been developed as part of the SWPPP for the Proposed Project. The SESC,
1 Fisher, D.W., Isachsen, Y.W., and Rickard, L.V., 1970, Geologic Map of New York State, consisting of 5
sheets: Niagara, Finger Lakes, Hudson-Mohawk, Adirondack, and Lower Hudson, New York State
Museum and Science Service, Map and Chart Series No. 15, scale 1:250,000. Accessed online at
https://mrdata.usgs.gov/geology/state/sgmc-unit.php?unit=NYYbqpq%3B1 01/29/2024.
800 East Main Street Redevelopment
07/10/2024 5-4 DRAFT
described in detail in Chapter 16, “Construction,” details the methods by which soil erosion and
runoff would be minimized during construction.
It is anticipated that rock removal will be required. Final determination of the need for rock
removal would be determined as construction plans are advanced and additional data collected. If
rock removal is necessary, hydraulic hammers could be used. While unlikely, any potential
blasting would be conducted in accordance with Chapter 124, “Blasting and Explosives,” of the
Town of Yorktown Code and pursuant to a blasting permit that would be obtained from the Town.
As per the Town Code, a notice of intent to blast would be delivered to all required recipients 30
days to 72 hours prior to blasting and a notice of blasting would be served 72 to 24 hours prior to
blasting. Finally, per Section 124-7 of the Town Code, blasting would only be conducted on
Monday through Saturday between 8:00 am and 5:00 pm.
D. MITIGATION MEASURES
Measures to mitigate potential impacts to geology, soils, and topography are included as part of
the Proposed Project. During the construction phase, a SESC Plan would be implemented to
mitigate potential soil erosion impacts. The SESC Plan is summarized in Chapter 16,
“Construction.” The Proposed Project would require the removal of approximately 81,836 cubic
yards of earthen material from the Project Site. However, final grading of the Proposed Project,
which would occur during the site plan approval phase of the Proposed Project, would be
anticipated to reduce this amount by refining the grading and building plans to better balance the
cut and fill. If a more balanced grading plan could not be achieved, and if all of the excess earthen
material were removed from the Project Site, it would take approximately 4,546 truck trips. These
trips would be spread throughout the duration of the Proposed Project’s construction, such that the
number of truck trips on any given day would be reduced to a level that would not affect traffic
operations. Finally, a SWPPP would be prepared to manage stormwater runoff after the Proposed
Project has been completed (see Chapter 10, “Stormwater Management”). With the implementation
of such measures, no significant adverse impacts to geology, soils, or topography are anticipated
as a result of the Proposed Project.
£¤6
Alb
y
n
Pl
B
a
r
g
e
r
S
t
B a n k Rd
LeeBlvd
O l d J e ff e r s o n V a ll e y R d
TaconicStPkwy
ServiceRd
Indian Hill R d
Tru m pPark
E
M
a
i
n
S
t
G A R Hwy
S t e p h e n S m i t h D r
ChE
ClC
PnD
CrC
PnB
ClCClD
ClD
ClB
PoB
CsD
ClB PoD
Sm
Sh
PnC
PnB
ChB ChC PnCSuBW
LeB PnD
ChB
LeB
Uf
CrC
ChDSuB
ChC
ChE
ChC
ClB
ChD
ChE
ChB
Sh
Sm
PnC PnB
CrC
ClD
ChD
CsD
ClC
ChBCrC
ChB
UbChBRdA
ChC
ChCFf
ChB
ChD
Uc
Uf
Uc
PnB
LeB
Ff
WdB
SuB
Sh
800 EAST MAIN STREET
NRCS Soils
Figure 5-1
0 1,000 FEET
Project Site
Soils
1.
1
0
.
2
4
Da
t
a
s
o
u
r
c
e
:
N
R
S
C
U
S
D
A
S
S
U
R
G
O
.
Soil Symbol - Soil
Name
ChB - Charlton fine
sandy loam, 3 to 8
percent slopes
ChC - Charlton fine
sandy loam, 8 to 15
percent slopes
ChD - Charlton fine
sandy loam, 15 to 25
percent slopes
ChE - Charlton loam, 25
to 35 percent slopes
ClB - Charlton fine
sandy loam, 3 to 8
percent slopes, very
stony
ClC - Charlton fine
sandy loam, 8 to 15
percent slopes, very
stony
ClD - Charlton loam, 15
to 25 percent slopes,
very stony
CrC - Charlton-Chatfield
complex, 0 to 15
percent slopes, very
rocky
CsD - Chatfield-
Charlton complex, 15 to
35 percent slopes, very
rocky
Ff - Fluvaquents-
Udifluvents complex,
frequently flooded
LeB - Leicester loam, 2
to 8 percent slopes,
very stony
PnB - Paxton fine sandy
loam, 3 to 8 percent
slopes
PnC - Paxton fine sandy
loam, 8 to 15 percent
slopes
PnD - Paxton fine sandy
loam, 15 to 25 percent
slopes
PoB - Paxton fine sandy
loam, 0 to 8 percent
slopes, very stony
PoD - Paxton fine sandy
loam, 15 to 25 percent
slopes, very stony
RdA - Ridgebury
complex, 0 to 3 percent
slopes
Sh - Sun loam
Sm - Sun loam,
extremely stony
SuB - Sutton loam, 3 to
8 percent slopes
Ub - Udorthents,
smoothed
Uc - Udorthents, wet
substratum
Uf - Urban land
W - Water
WdB - Woodbridge
loam, 3 to 8 percent
slopes
800 EAST MAIN STREET
Topography
Figure 5-2
0 500 FEET
Project Site
Project Site Slopes
0-10%
10-15%
Greater than 15%
5.
1
5
.
2
4
Da
t
a
s
o
u
r
c
e
:
N
Y
S
H
i
g
h
R
e
s
o
l
u
t
i
o
n
D
E
M
s
.
t
r
k
og
800 EAST MAIN STREET
Surficial Geology
Figure 5-3
0 1 Miles
Project Site
Surficial Geology
k - Kame deposits
og - Outwash sand and gravel
r - Bedrock
t - Till
1.
1
0
.
2
4
Da
t
a
s
o
u
r
c
e
:
N
e
w
Y
o
r
k
S
t
a
t
e
M
u
s
e
u
m
;
L
o
w
e
r
H
u
d
s
o
n
S
u
r
f
i
c
i
a
l
G
e
o
l
o
g
y
£¤6
bg
bqpc
Cpg
800 EAST MAIN STREET
Bedrock Geology
Figure 5-4
0 1 Miles
Project Site
Bedrock Geology
Cpg - Poughquag Quartzite
bg - Biotite granite gneiss
bqpc - Biotite-quartz-plagioclase paragneis
1.
1
0
.
2
4
Da
t
a
S
o
u
r
c
e
:
N
e
w
Y
o
r
k
S
t
a
t
e
M
u
s
e
u
m
;
L
o
w
e
r
H
u
d
s
o
n
B
e
d
r
o
c
k
G
e
o
l
o
g
y
.